Wind Turbine Blades En Route to Bellevue Gold Project Site

Blogs, ESG, In the News, News

Wind Turbine Blades En Route to Bellevue Gold Project Site

Home News and Blog For a second consecutive year Asian Power Awards have recognised Zenith Energy as Independent PThe first components of the four GW165/6.0MW Goldwind turbines have started arriving at the Bellevue Gold Project site, with the turbine blades successfully transported from Geraldton Port. This milestone marks significant progress in the development of the […]

December 05, 2024


clock7min

For a second consecutive year Asian Power Awards have recognised Zenith Energy as Independent PThe first components of the four GW165/6.0MW Goldwind turbines have started arriving at the Bellevue Gold Project site, with the turbine blades successfully transported from Geraldton Port. This milestone marks significant progress in the development of the 88MW hybrid power station at the Bellevue Gold Project.

Zenith Energy, under a 15-year power purchase agreement, will finance, build, own, and operate the hybrid power solution, which consists of wind (24MW), solar (27MW), thermal (24MW), and a Battery Energy Storage System (15 MW/33 MWh). The innovative energy system also includes LNG storage and regasification, and synchronous condensers to stabilise the network. This hybrid solution will provide up to 80% of the project’s energy needs from renewable sources, aligning with Bellevue’s goal to become Australia’s first carbon-neutral gold producer.

The hybrid power station will operate on up to 100% renewable energy during periods of optimal wind and solar conditions, supporting Bellevue’s decarbonisation objectives by synchronising milling activities with renewable energy availability.

Share this article

Home

News and Blog

Exciting Milestone at the Mt Weld Hybrid Power Station

Blogs, ESG, In the News, News, Project Announcements & Updates

Exciting Milestone at the Mt Weld Hybrid Power Station

Home News and Blog Since 2015 Zenith has quietly worked to develop the concepts needed to reduce emissions, while Zenith Energy is pleased to announce that commissioning has commenced for the Diesel component of the Mt Weld Hybrid Power Project for Lynas Rare Earths Ltd. This marks an important step in the journey towards delivering […]

December 03, 2024


clock7min

Since 2015 Zenith has quietly worked to develop the concepts needed to reduce emissions, while Zenith Energy is pleased to announce that commissioning has commenced for the Diesel component of the Mt Weld Hybrid Power Project for Lynas Rare Earths Ltd. This marks an important step in the journey towards delivering a cutting-edge 65 MW hybrid power solution.

The project integrates:
5 MW of backup diesel generation (now commissioning),
17 MW high-efficiency gas-fired power plant (Q1 CY2025),
7 MW of solar power (Q3 CY2025),
24 MW wind farm (Q1 CY2026), and
12 MW/12 MWh Battery Energy Storage System (Q3 CY2025)

Once complete, the power station will enable up to 70% renewable energy, including the innovative ‘Engine Off’ capability for 100% renewable operation when conditions allow. This transition supports Lynas Rare Earths Ltd decarbonisation goals and commitment to reducing greenhouse gas emissions.

Diesel component of the Mt Weld Hybrid Power Project

Share this article

Home

News and Blog

Wind Turbine Blades Arrive at Geraldton Port for the Bellevue Gold Project

In the News, News, Project Announcements & Updates

Wind Turbine Blades Arrive at Geraldton Port for the Bellevue Gold Project

Home News and Blog The wind turbine blades—four GW165/6.0MW Goldwind turbines—have arrived at Geraldton Port, marking a key milestone in the development of an 88MW hybrid power station for the Bellevue Gold Project. Under a 15-year power purchase agreement, Zenith Energy will finance, build, own, and operate this hybrid solution, which integrates wind, solar, thermal, and […]

November 18, 2024


clock7min

The wind turbine blades—four GW165/6.0MW Goldwind turbines—have arrived at Geraldton Port, marking a key milestone in the development of an 88MW hybrid power station for the Bellevue Gold Project. Under a 15-year power purchase agreement, Zenith Energy will finance, build, own, and operate this hybrid solution, which integrates wind, solar, thermal, and battery storage to supply up to 80% of the project’s energy needs from renewable sources.

Once operational, the station will further enable Bellevue Gold Mine to operate on up to 100% renewable energy during optimal conditions, supporting their goal to become Australia’s first carbon-neutral gold producer and furthering our commitment to sustainable, off-grid energy for the resources sector.

Share this article

Home

News and Blog

Zenith Energy 3rd Globally in IPP ESG Performance (GRESB)

Blogs, ESG, In the News, News

Zenith Energy 3rd Globally in IPP ESG Performance (GRESB)

Home News and Blog We are excited to announce that Zenith Energy has been ranked 3rd globally among 25 peers in the Power Generation x-Renewables category: Independent Power Producers sector in the 2024 GRESB Infrastructure Asset Assessment. GRESB, a leading independent organisation, provides validated ESG performance data and peer benchmarks for investors. This year’s assessment spanned 720 assets across […]

November 07, 2024


clock7min

We are excited to announce that Zenith Energy has been ranked 3rd globally among 25 peers in the Power Generation x-Renewables category: Independent Power Producers sector in the 2024 GRESB Infrastructure Asset Assessment.

GRESB, a leading independent organisation, provides validated ESG performance data and peer benchmarks for investors. This year’s assessment spanned 720 assets across 81 countries, representing a remarkable $1.58 trillion USD in asset value

This remarkable achievement underscores Zenith Energy’s dedication to leading in ESG and sustainability in the markets we serve. It also highlights the commitment and hard work of all Zenith’s staff who have made this accomplishment possible. 

The full public benchmark data was released on October 15. 

Share this article

Home

News and Blog

Zenith Energy Wins Big at the Asian Power Awards 2024

Blogs, ESG, In the News, News

Zenith Energy Wins Big at the Asian Power Awards 2024

Home News and Blog For a second consecutive year Asian Power Awards have recognised Zenith Energy as Independent Power Producer of the Year – Australia. Zenith was also awarded Solar Power Project of the Year – Australia, and Wind Power Project of the Year – Australia for 2024 both located at the Kathleen Valley Hybrid […]

October 29, 2024


clock7min

For a second consecutive year Asian Power Awards have recognised Zenith Energy as Independent Power Producer of the Year – Australia. Zenith was also awarded Solar Power Project of the Year – Australia, and Wind Power Project of the Year – Australia for 2024 both located at the Kathleen Valley Hybrid Power System delivering a minimum 60% renewable energy for Liontown Resources Limited.

These awards highlight Zenith’s leadership in the energy transition of Australia’s mining sector.

Learn more at: Zenith Energy bags three accolades at Asian Power Awards 2024 | Asian Power

Share this article

Home

News and Blog

Wärtsilä – Zenith Contract Signing Ceremony: Parts Predict & Operational Support Services for Zenith Energy

Blogs, In the News, News, Project Announcements & Updates

Wärtsilä – Zenith Contract Signing Ceremony: Parts Predict & Operational Support Services for Zenith Energy

On Wednesday, 16 October, Zenith Energy and Wärtsilä formalised a long-term agreement at Zenith’s corporate offices in Perth.

October 25, 2024


clock7min

On Wednesday, 16 October, Zenith Energy and Wärtsilä formalised a long-term agreement at Zenith’s corporate offices in Perth.

This 4-year Parts Predict & Operational Support Services Agreement is a strategic step for ensuring the optimal performance of the Wärtsilä medium- speed heavy-duty, flexible engines in service at Zenith’s power stations.

This agreement highlights a continued focus on reliability, efficiency, and proactive maintenance of critical infrastructure, which is essential for meeting the energy demands of remote power generation projects in Australia’s mining and resources sectors.

Hamish Moffat, Managing Director of Zenith Energy, stated:
“This agreement builds on our long-standing partnership with Wartsila in the remote IPP space, supporting power generation projects in the Australian resources and mining sectors. It aligns with our philosophy of fostering long-term partnerships with key OEM partners to deliver value to Zenith, our clients, and stakeholders.”

Rey Santos, Managing Director of Wärtsilä Australia, commented:
We are excited about this agreement and to further strengthen the valuable and established
relationship we have with Zenith. Wärtsilä has a strong global track record of various types of
agreements with skilled professionals, whose knowledge and expertise can be utilized to bring
additional benefits and value for this partnership. I look forward to expanding and deepening our
collaboration.”

This partnership ensures the continuous operation of critical energy assets, helping to meet operational targets and deliver long-term value.

Share this article

Home

News and Blog

A Milestone in Australia’s Renewable Energy Transition

Blogs, ESG, In the News, News, Project Announcements & Updates

A Milestone in Australia’s Renewable Energy Transition

Home News and Blog On 9 October, we held the official ‘Opening of Australia’s Largest Off-Grid Wind Farm and Market-Leading Hybrid Power System’. The Honourable Reece Whitby, Minister for Energy, Environment and Climate Action formally opened this milestone power system highlighting that two Western Australian companies in Zenith Energy and Liontown Resources Limited were leading the […]

October 14, 2024


clock2min

On 9 October, we held the official ‘Opening of Australia’s Largest Off-Grid Wind Farm and Market-Leading Hybrid Power System’. The Honourable Reece Whitby, Minister for Energy, Environment and Climate Action formally opened this milestone power system highlighting that two Western Australian companies in Zenith Energy and Liontown Resources Limited were leading the energy transition for Australia’s mining sector with an energy solution that provides a glide path for a broader net zero Goldfields region.

Alongside the Minister, the event featured speeches from Hamish Moffat, CEO of Zenith Energy, and Doug Walker, Executive Chairman of Zenith Energy, as well as Kirit Chauhan, General Manager Project Development at Liontown Resources Limited, who spoke about the partnership with the Tjiwarl Native Title Holders. The unveiling of the plaque by the Minister alongside Tjiwarl Chairman, Brett Lewis, reflecting the important involvement of the Indigenous community in this project. With a capacity of 95MW, this system will enable Liontown to operate with a minimum 60% emissions-free energy.

Talbot Muir (Traditional Owner), Brett Lewis (Tjiwarl Chairman), Kirit Chauhan (General Manager Development, Liontown Resources), Doug Walker (Executive Chairman, Zenith Energy), Reece Whitby (Minister for Environment and Climate Action), Hamish Moffat (CEO and Managing Director, Zenith Energy).
Share this article

Home

News and Blog

Zenith Energy Advances the Jundee Renewables Project

Blogs, ESG, In the News, News, Project Announcements & Updates

Zenith Energy Advances the Jundee Renewables Project

Home News and Blog Zenith Energy has successfully completed the installation of four GW165/6.0MW Goldwind wind turbines at Northern Star Resources Limited’s Jundee renewables project. This 24MW wind farm is now entering the commissioning phase and will soon be integrated into a comprehensive hybrid renewable energy solution. This hybrid system combines wind energy with solar […]

October 04, 2024


clock1min

Zenith Energy has successfully completed the installation of four GW165/6.0MW Goldwind wind turbines at Northern Star Resources Limited’s Jundee renewables project. This 24MW wind farm is now entering the commissioning phase and will soon be integrated into a comprehensive hybrid renewable energy solution.

This hybrid system combines wind energy with solar power and battery storage, working alongside the existing gas power station. It is designed to provide reliable, continuous energy for the Jundee mining operation, significantly reducing its reliance on fossil fuels and cutting greenhouse gas emissions by more than 50%.

The Jundee project is a key milestone in Zenith Energy’s ongoing commitment to decarbonising the mining industry. By delivering sustainable, off-grid power solutions, Zenith Energy is helping transform how the resources sector in Western Australia operates, paving the way for a future where mining and sustainability go hand in hand.

Zenith’s IGO Nova Solar

Share this article

Home

News and Blog

Afternoon on the Green 

News

Afternoon on the Green 

Home News and Blog On Saturday (7th September), Zenith Energy General Manager – Connected Energy, Jason Good & Casey Gibson, Customer Services Manager attended the Afternoon on the Green event hosted by Cedar Woods at Eglinton Village.  The event brought together representatives from local community stakeholder groups, including Cedar Woods, the City of Wanneroo, Yanchep […]

September 15, 2024


clock7min

On Saturday (7th September), Zenith Energy General Manager – Connected Energy, Jason Good & Casey Gibson, Customer Services Manager attended the Afternoon on the Green event hosted by Cedar Woods at Eglinton Village. 

The event brought together representatives from local community stakeholder groups, including Cedar Woods, the City of Wanneroo, Yanchep Community Garden, Eglinton Village Energy a Zenith Energy Company, and local primary schools. It was a great opportunity for future residents of Eglinton Village to interact with these representatives and ask questions. 

Eglinton Village Energy is a market leading energy solution for home owners in Eglinton Village delivering lower cost power and more green energy.  

For more information, visit the EVE project page: https://eglintonvillageenergy.com.au/ 

Afternoon on the Green 

Share this article

Home

News and Blog

Zenith Energy at the Women in Energy & Renewables Summit in Sydney

News

Zenith Energy at the Women in Energy & Renewables Summit in Sydney

Home News and Blog Three members of Zenith Energy, Abby Kenward (Executive, Human Resources), Corina Da Silva (Contract Specialist), and Sabrina Teh (Contracts Manager), attended the Women in Renewables Conference in Sydney. This event brings together industry leaders and professionals to explore the challenges and opportunities for women in the renewable energy sector, promoting inclusion […]

September 15, 2024


clock7min

Three members of Zenith Energy, Abby Kenward (Executive, Human Resources), Corina Da Silva (Contract Specialist), and Sabrina Teh (Contracts Manager), attended the Women in Renewables Conference in Sydney.

This event brings together industry leaders and professionals to explore the challenges and opportunities for women in the renewable energy sector, promoting inclusion and gender equality in this rapidly growing field.

At Zenith Energy, we are proud to support our team’s involvement in events that drive female representation in the energy industry.

For more information about the conference, visit the official website: https://womeninenergyandrenewablessummit.com.au/

Zenith Energy at the Women in Energy & Renewables Summit in Sydney

Share this article

Home

News and Blog

Zenith Energy Proud Sponsor of Belmont Art 2024

Blogs, In the News, News

Zenith Energy Proud Sponsor of Belmont Art 2024

Home News and Blog Zenith Energy was pleased to sponsor the 2024 City of Belmont Art Awards, an event that brings the community together to engage with art and culture. The Awards feature a variety of artworks from across the state, including drawings, paintings, photography, textiles, sculptures, and ceramics. This year’s exhibition includes 300 artworks […]

September 11, 2024


clock1min

Zenith Energy was pleased to sponsor the 2024 City of Belmont Art Awards, an event that brings the community together to engage with art and culture. The Awards feature a variety of artworks from across the state, including drawings, paintings, photography, textiles, sculptures, and ceramics. This year’s exhibition includes 300 artworks selected from over 580 entries, representing youth, emerging artists, and established professionals.

We were part of the Opening Night event, where Doug Walker, Zenith Energy’s Executive Chairman, presented the Belmont Resident award to Janice Oliver for her winning artwork.

The free, two-week exhibition is being held at The Glasshouse from Friday, 30 August to Saturday, 14 September.

Share this article

Home

News and Blog

Progress at Jundee: August 2024

Blogs, ESG, In the News, News, Project Announcements & Updates

Progress at Jundee: August 2024

Home News and Blog The installation of WTG 01 at our Jundee project, in collaboration with Northern Star, has officially begun. On August 25th, 2024, having completed WTG 04, WTG 03 and WGT 02 we successfully installed the first three sections. This marks a significant milestone in our journey to decarbonise Jundee.  Share this article […]

September 04, 2024


clock1min

The installation of WTG 01 at our Jundee project, in collaboration with Northern Star, has officially begun. On August 25th, 2024, having completed WTG 04, WTG 03 and WGT 02 we successfully installed the first three sections. This marks a significant milestone in our journey to decarbonise Jundee. 

Zenith’s Jundee Project

Share this article

Home

News and Blog

Zenith Energy Highly Commended for Portfolio Transformation at Reuters Global Energy Transition Awards 2024

Blogs, ESG, In the News, News

Zenith Energy Highly Commended for Portfolio Transformation at Reuters Global Energy Transition Awards 2024

Home News and Blog Zenith Energy has been highly commended for its Portfolio Transformation at the Reuters Events Energy Transition Awards held last month in New York.The Portfolio Transformation Award within “The Company of the Net Zero Future” category recognised Zenith’s achievements in contracting and constructing most of Australia’s off-grid high fraction renewable hybrid power solutions for […]

August 14, 2024


clock1min

Zenith Energy has been highly commended for its Portfolio Transformation at the Reuters Events Energy Transition Awards held last month in New York.
The Portfolio Transformation Award within “The Company of the Net Zero Future” category recognised Zenith’s achievements in contracting and constructing most of Australia’s off-grid high fraction renewable hybrid power solutions for Australia’s mining sector; and its innovative grid-connected high-fraction renewable energy microgrids in Perth’s metropolitan and regional areas.

Congratulations to TAQA Group who won the Portfolio Transformation Award for a CapEx investment commitment of $20 billion towards portfolio transformation by 2030. Congratulations also to all finalists for their dedication and contributions to the energy transition.

Share this article

Home

News and Blog

Bellevue Gold Power System Milestone Update

Blogs, ESG, In the News, News, Project Announcements & Updates

Bellevue Gold Power System Milestone Update

Home News and Blog Zenith Energy’s hybrid power system for Bellevue Gold is on track to become Australia’s highest renewable energy fraction off-grid power solution with the latest milestone being completion of the concrete pour for the first wind turbine. Share this article You might also like these…

August 12, 2024


clock1min

Zenith Energy’s hybrid power system for Bellevue Gold is on track to become Australia’s highest renewable energy fraction off-grid power solution with the latest milestone being completion of the concrete pour for the first wind turbine.

Share this article

Home

News and Blog

Zenith Energy Named Finalist for 2024 Energy Innovation of the Year Award

Blogs, ESG, In the News, News

Zenith Energy Named Finalist for 2024 Energy Innovation of the Year Award

Home News and Blog Zenith Energy‘s Eglinton Village Energy (EVE) project is a finalist for the 2024 Energy Innovation of the Year Award at WA Energy Awards, organised by The Australian Institute of Energy. These awards recognise outstanding achievements in the energy sector, celebrating companies that lead the way in innovation, sustainability, and excellence. This […]

August 08, 2024


clock1min

Zenith Energy‘s Eglinton Village Energy (EVE) project is a finalist for the 2024 Energy Innovation of the Year Award at WA Energy Awards, organised by The Australian Institute of Energy. These awards recognise outstanding achievements in the energy sector, celebrating companies that lead the way in innovation, sustainability, and excellence.

This nomination underscores our commitment to leading the energy transition, delivering sustainable energy solutions.

The winners of the different categories will be announced on 15 August 2024 at Fraser’s Restaurant in Kings Park.

For more information, visit: Energy Week WA (energywa.org.au)

Share this article