Mt Weld Progressing Fast
Blogs, ESG, In the News, News

Mt Weld Progressing Fast

Mt Weld Progressing Fast

April 14, 2025


clock7min

Alongside the successful commissioning of the gas generation plant, Zenith Energy is making rapid progress on the renewable energy infrastructure at Lynas Rare Earths Ltd’ Mt Weld operations.


✔️ Commissioning Complete – The 5 x 3.4MW gas gensets were fully commissioned and tested ahead of schedule, with the facility handed over on 1 March 2025.
✔️ Solar module installation set to begin in March.
✔️ BESS footings completed, with battery delivery expected in April.
✔️ Wind farm civil works progressing ahead of schedule.
✔️ Solar farm on track for completion in the first half of FY26.
✔️ Wind farm progressing tracking ahead of the 2H FY26 target.


With each milestone met ahead of schedule, Zenith is driving a reliable, lower-carbon future for Lynas —seamlessly integrating gas, solar, wind, and battery storage.