Alongside the successful commissioning of the gas generation plant, Zenith Energy is making rapid progress on the renewable energy infrastructure at Lynas Rare Earths Ltd’ Mt Weld operations.
✔️ Commissioning Complete – The 5 x 3.4MW gas gensets were fully commissioned and tested ahead of schedule, with the facility handed over on 1 March 2025.
✔️ Solar module installation set to begin in March.
✔️ BESS footings completed, with battery delivery expected in April.
✔️ Wind farm civil works progressing ahead of schedule.
✔️ Solar farm on track for completion in the first half of FY26.
✔️ Wind farm progressing tracking ahead of the 2H FY26 target.
With each milestone met ahead of schedule, Zenith is driving a reliable, lower-carbon future for Lynas —seamlessly integrating gas, solar, wind, and battery storage.
Zenith Energy is leading the way in high-fraction renewable hybrid power solutions, ensuring mining operations transition to cleaner, more sustainable energy sources.