Home

Case Studies

Mt Weld

Mt Weld

The project integrates 7 MW of solar, 24 MW of wind, and a 12 MW/12 MWh BESS, enabling "Engine Off" capabilities. The goal is to cover up to 70% of the project's energy needs with renewable energy by 2026, reducing its reliance on diesel and lowering emissions.

Project Background

The Mt Weld Project, operated by Lynas Rare Earths, is a significant rare earths mining operation in Western Australia. The project is transitioning from diesel to a hybrid gas and renewable energy solution to reduce greenhouse gas emissions and lower power costs.

Renewable Integration

The project integrates 7 MW of solar, 24 MW of wind, and a 12 MW/12 MWh BESS, enabling “Engine Off” capabilities. The goal is to cover up to 70% of the project’s energy needs with renewable energy by 2026, reducing its reliance on diesel and lowering emissions.

How Zenith is Leading the Sector

Zenith Energy is spearheading the renewable transition at Mt Weld with a 65 MW hybrid power station, featuring wind, solar, and battery storage. By overseeing the design, construction, and operation of this station, Zenith is solidifying its position as a leader in renewable energy solutions within the mining sector, with over 100 MW of contracted wind capacity.

Installed capacity

  • Thermal: 17 MW high-efficiency gas-fired power plant, plus 5 MW of backup diesel generation
  • Solar: 7 MW
  • Wind: 24MW, Consisting of 4 x 6MW Goldwind Turbines with a rotor Diameter of 165M, and a total height of 212M.
  • BESS: 12 MW/12 MWh Battery Energy Storage System
  • Synchronous condensers: 2 x 5MVAr Syncon.
  • ‘Engine Off’ enabled – the ability to operate on 100% renewable energy when conditions allow.
  • Renewable energy fraction: The goal is for approximately 70% of the project’s energy needs to be met by renewable energy.

Commercial operation date (COD)

  • Diesel Powerstation is already complete
  • Gas Powerstation is scheduled for Q1 CY2025.
  • Solar and BESS is scheduled for Q3 CY2025.
  • The wind farm is scheduled to commence commercial operations in Q1 2026.

Contract term

The Power Purchase Agreement (PPA) is for a 15-year term, starting from the commercial operation of the wind farm.

Client’s decarbonisation objective

Lynas Rare Earths is committed to reducing its greenhouse gas emissions by transitioning from diesel to a gas-fired hybrid renewable power station. The decommissioning of the existing diesel power plant will occur once the gas-fired station is operational. This transition aligns with Lynas’ goal of lowering emissions while also reducing the cost of power compared to a thermal-only solution.

Additional information

Zenith Energy is responsible for the design, construction, ownership, operation, and maintenance of the Mt Weld Hybrid Power Station, which will have a total installed capacity of 65 MW upon completion. Early construction works began in 2023 under Preliminary and Early Works Agreements with Lynas. This collaboration with Lynas further solidifies Zenith Energy’s leadership in the renewable energy transition within the mining sector, with contracted wind capacity now exceeding 100 MW.

Project name
Mt Weld
Location

Mt Weld, Western Australia, Australia

Client
Lynas Rare Earths
Capacity
65 MW (Hybrid System: 17 MW Gas, 5 MW Diesel, 7 MW Solar, 24 MW Wind, 12 MW/12 MWh BESS)
Fuel source
BESS, Gas, Hybrid Renewable, Solar PV, Wind
CONTRACT

15-year Power Purchase Agreement (PPA)

COMMENCEMENT

Gas power station scheduled for Q1 2025, solar and BESS in Q3 2025, wind farm in Q1 2026

Home

Case Studies

Kathleen Valley

Kathleen Valley

The project features 17 MW of solar, 30 MW of wind, and a 17 MW/20 MWh BESS, which enable "Engine Off" capabilities. The hybrid system is designed to meet up to 80% of the project's energy needs through renewable energy in the near future, significantly reducing the mine's carbon footprint.

Project Background

The Kathleen Valley Project is a lithium mining operation led by Liontown Resources. The project focuses on integrating a hybrid power solution that maximises renewable energy usage to support the energy-intensive mining process, reflecting Liontown’s commitment to sustainability.

Renewable Integration

The project features 17 MW of solar, 30 MW of wind, and a 17 MW/20 MWh BESS, which enable “Engine Off” capabilities. The hybrid system is designed to meet up to 80% of the project’s energy needs through renewable energy in the near future, significantly reducing the mine’s carbon footprint.

How Zenith is Leading the Sector

Zenith Energy has developed Australia’s largest operating off-grid hybrid power system for this project, combining renewable energy sources with thermal generation. This solution not only demonstrates Zenith’s leadership in integrating renewables in remote mining operations but also aligns with Australia’s energy transition goals.

Installed capacity

  • Thermal: Gas – 27MW, Diesel 5MW, Total 32MW
  • LNG Storage and Regasification Facility
  • Solar: 17 MW
  • Wind: 30MW, Consisting of 5 x 6MW Goldwind Turbines with a rotor Diameter of 165M, and a total height of 212M.
  • BESS: Battery Energy Storage System of 17MW/20 MWh
  • Synchronous condensers: 3 x 2.8MVAr Syncons.
  • ‘Engine Off’ enabled – the ability to operate on 100% renewable energy when conditions allow.

Renewable energy fraction

The goal is for approximately 80% of the project’s energy needs to be met by renewable energy in the near future.

Commercial operation date (COD)

The hybrid power plant was officially inaugurated on 9th October 2024 but has been operating since early 2024.

Contract term

Long-term Power Purchase Agreement (PPA) 15 years.

Client’s decarbonisation objective

Liontown Resources aims to minimise its carbon footprint by using renewable energy in its mining operations.

Additional information

The Kathleen Valley Project, integrates a hybrid power solution that is the largest operating off-grid hybrid power system in Australia. It includes solar, wind, and battery energy storage alongside thermal generation. This solution supports Liontown Resources’ commitment to sustainability and its goal of reducing carbon emissions in line with Australia’s energy transition efforts.

Project name
Kathleen Valley
Location

Kathleen Valley, Western Australia, Australia

Client
Liontown Resources
Capacity
79 MW (Hybrid System: 27 MW Gas, 5 MW Diesel, 17 MW Solar, 30 MW Wind, 17 MW/20 MWh BESS)
Fuel source
BESS, Gas, Hybrid Renewable, Solar PV, Wind
CONTRACT

15-year Power Purchase Agreement (PPA)

COMMENCEMENT

Inaugurated on 9th October 2024, operational since early 2024

Home

Case Studies

Bellevue Gold

Bellevue Gold

The project includes 27 MW of solar, 24 MW of wind, and a 15 MW/33 MWh Battery Energy Storage System (BESS), enabling "Engine Off" operation. This setup allows the project to run entirely on renewable energy during favorable conditions, meeting approximately 80% of its energy needs through renewables.

Project Background

The Bellevue Gold Project is a large-scale gold mining operation in Western Australia, aiming to lead the sector in decarbonization. The project includes a hybrid power station that integrates renewable energy sources alongside traditional thermal generation to achieve significant reductions in carbon emissions.

Renewable Integration

The project includes 27 MW of solar, 24 MW of wind, and a 15 MW/33 MWh Battery Energy Storage System (BESS), enabling “Engine Off” operation. This setup allows the project to run entirely on renewable energy during favorable conditions, meeting approximately 80% of its energy needs through renewables.

How Zenith is Leading the Sector

Zenith Energy is setting the standard by constructing a 90 MW hybrid power station that combines solar, wind, and battery energy storage with thermal generation. Their innovative approach supports Bellevue’s goal of becoming Australia’s first carbon-neutral gold producer. The collaboration with Tjiwarl Contracting Services also highlights Zenith’s commitment to Indigenous engagement.

Installed capacity

  • Thermal: Gas – 15MW, Diesel 9MW, Total 24MW
  • LNG Storage and Regasification Facility
  • Solar: 27 MW
  • Wind: 24MW, Consisting of 4 x 6MW Goldwind Turbines with a rotor Diameter of 165M, and a total height of 212M.
  • BESS: Battery Energy Storage System of 15 MW/33 MWh
  • Synchronous condensers: 1 x 5MVAr Syncron.
  • ‘Engine Off’ enabled – the ability to operate on 100% renewable energy when conditions allow.

Renewable energy fraction

The goal is for approximately 80% of the project’s energy needs to be met by renewable energy.

Commercial operation date (COD)

May 2024.

Contract term

Power Purchase Agreement (PPA) for an initial term of 15 years.

Client’s decarbonisation objective

To significantly reduce carbon emissions by primarily operating on renewable energy. Bellevue aims to become Australia’s first carbon-neutral gold producer by utilising high levels of renewable energy and synchronising milling activities with renewable energy availability.

Additional information

Zenith Energy and Bellevue Gold have partnered to establish an innovative 90 MW hybrid power station for the Bellevue Gold Project. The hybrid power station will consist of wind and solar generation, thermal generation, and battery storage, enabling the project to operate on 100% renewable energy during periods of high renewable generation. This partnership also advances the Tjiwarl Katu Power Joint Venture between Zenith Energy and Tjiwarl Contracting Services, which represents the Tjiwarl Aboriginal Corporation, the traditional owners of the land where the Bellevue Gold Project is located.

Project name
Bellevue Gold
Location

Western Australia, Australia

Client
Bellevue Gold
Capacity
90 MW hybrid power station that combines solar, wind, and battery energy storage with thermal generation.
Fuel source
BESS, Gas, Hybrid Renewable, Solar PV, Wind
CONTRACT

15-year Power Purchase Agreement (PPA)

COMMENCEMENT

Commercial operation date (COD) May 2024

Home

Case Studies

Jundee

Jundee

Northern Star Resources’ Jundee mine is an underground mining operation located in the Northern Goldfields region of Western Australia approximately 45 kms north-east of Wiluna and approximately 520 kms north of Kalgoorlie.

Project Background

Northern Star Resources’ Jundee mine is an underground mining operation located in the Northern Goldfields region of Western Australia approximately 45 kms north-east of Wiluna and approximately 520 kms north of Kalgoorlie.

Northern Star Resources is an ASX listed, global–scale Australian gold producer with world class projects within Australia and North America. The company owns and operates three world class gold production centres in Kalgoorlie, Yandal and Pogo (Jundee, 2022).

Zenith is providing 46.6MW of power generation through the use of natural gas fuelled generators.

Zenith commenced work on the power station in 2016.

Renewable Integration

The project incorporates 17 MW of solar, 24 MW of wind, and a 12 MW/12 MWh BESS. This hybrid system is expected to meet 56% of the project’s energy needs through renewable sources, significantly cutting emissions.

How Zenith is Leading the Sector

Zenith Energy’s renewable energy Power Purchase Agreement (PPA) with Northern Star Resources at Jundee supports the transition to a lower-carbon energy system. Zenith’s innovative renewable energy retrofit has positioned the company as a key player in reducing carbon intensity across the mining sector, further advancing their net-zero milestones.

Installed capacity

  • Thermal: 43 MW through high-efficiency gas generation and diesel
  • Solar:17 MW
  • Wind: 24MW, Consisting of 4 x 6MW Goldwind Turbines with a rotor Diameter of 165M, and a total height of 212M.
  • BESS: 12 MW/12 MWh Battery Energy Storage System
  • Synchronous condensers: No Syncons Installed
  • Renewable energy fraction: The goal is for approximately 55% of the project’s energy needs to be met by renewable energy.

Commercial operation date (COD)

The Original Jundee power station began operations in 2016, with the first hybrid components commissioned in early 2024.

Contract term

Long-term Power Purchase Agreement (PPA) under a Build, Own, operate (BOO) model, recently extended until 2039.

Client’s decarbonisation objective

Northern Star Resources aims to significantly reduce its carbon emissions by incorporating renewable energy sources into the Jundee mine operation. With the addition of wind, solar, and battery storage, the Jundee site will cover 56% of its energy needs with renewable sources. This aligns with Zenith Energy’s goal to reduce its carbon intensity by 20% by 2025, from a 2020 baseline, which includes scope 1, 2, and 3 emissions.

Additional information

Zenith Energy has signed a renewable energy Power Purchase Agreement with Northern Star Resources for the Jundee operation. This PPA will support Zenith Energy’s interim net zero milestones and strengthen its relationship with Northern Star, with the renewable energy retrofit expected to significantly cut carbon emissions and increase the use of renewables at the mine.

PROJECT NAME
Jundee
LOCATION

Northern Goldfields, WA

CLIENT
NSR
CAPACITY
46.6 MW
ENERGY SOURCE
BESS, Diesel, Gas, Solar PV, Wind

Home

Case Studies

King of The Hills

King of The Hills

The King of the Hills underground gold mine is 100% owned by Red 5 and is located 28km north of the town of Leonora in the Eastern Goldfields region of Western Australia.

Project Background

The King of the Hills underground gold mine is 100% owned by Red 5 Limited and is located 28km north of the town of Leonora in the Eastern Goldfields region of Western Australia.

Red 5 Limited is an ASX listed gold producer who also operates the Darlot Gold Mine, located 80km south of King of the Hills.

Zenith Energy is providing a power solution which will use a combination of gas sets, solar PV, and Battery Energy Storage System (BESS) to generate a capacity of 30MW.

The power supply to the site commenced in March 2022 with an initial term of 10 years.

Renewable Integration

The King of The Hills site will integrate renewable technology and will be the first to use the modular 5B Maverick solar solution, a big step in Zenith Energy’s objective to create a fleet of relocatable renewables.

The station is also designed to allow for further integration of additional renewable generation for future operations and expansions.

“We are pleased to have signed the Power Purchase Agreement with Zenith Energy, an experienced power producer which provided us with a compelling hybrid thermal and sustainable power solution that includes renewable energy. “Zenith Energy’s combination of a gas and so lar power station, supported by a Battery Energy Storage System, provides the efficiency and stability required for the processing plant and infrastructure to enable King of the Hills to be a long – life, low-cost gold produce”

Red 5 Limited Managing Director, Mark Williams

Project name
King of The Hills
Location

Eastern Goldfields, WA

Client
Red 5
Capacity
31 MW
Energy source
BESS, Gas, Solar PV

Home

Case Studies

Warrawoona

Warrawoona

Calidus Resources is an ASX listed gold company that is developing the 1.5Moz Warrawoona Gold Project in the East Pilbara district of Western Australia.

Project Background

Calidus Resources is an ASX listed gold company that is developing the 1.5Moz Warrawoona Gold Project in the East Pilbara district of Western Australia.

The Zenith Energy solution for this project was the construction of a 19MW power station, with primary power provided by a 10MW gas station with full diesel redundancy.

Power station comprises;

  • LNG Storage Facility
  • 8 x KTA50s, each with a capacity of 1.02MW
  • 4 x Jenbacher 616 each with a capacity of 2.68MW

Renewable Integration

After finalising the PPA, Zenith Energy was engaged by Calidus Resources to assess the viability of deploying a solar solution to offset emissions

The renewable solution that Zenith Energy developed included the installation of a:

  • 4MW DC Solar Farm and,
  • A 3MW/3MWh AC Battery Energy Storage System (BESS)

The solar farm will utilise modular technology, adding to Zenith Energy’s fleet of relocatable renewables.

The hybrid power station configuration will result in a reduction in gas use, which in turn results in a reduction in emissions, around 13 percent less than the initially contracted gas only station.

“Calidus is committed to carbon reduction as part of its ESG policy. This renewable micro grid is a cornerstone to our carbon reduction plan which includes the use of LNG not diesel and the ability of the LNG gensets to use up to 25% hydrogen. We are pleased to extend the relationship with Zenith to incorporate this renewables project, and look forward to its construction in the second half of this year”

Calidus Managing Director, Dave Reeves

Project Updates

PROJECT NAME
Warrawoona
LOCATION

East Pilbara, WA

CLIENT
Calidus
CAPACITY
23 MW
ENERGY SOURCE
BESS, Gas, Solar PV

Home

Case Studies

Tanami

Tanami

Newmont’s Tamami Gold Mine is an underground mine located 540 km north-west of Alice Springs, Northern Territory, Australia.

Project Background

Newmont’s Tanami Gold Mine is an underground mine located 540 km north-west of Alice Springs, Northern Territory, Australia.

Zenith currently operates two power stations at the Newmont Tanami site; the Dead Bullock Soak (DBS) station and the Granites Power Station (GTS).

The two stations are located 42km apart and are joined by 66kV overhead powerlines.

The two power stations combined to have a capacity of 101.5MW and were commenced in 2018.

Renewable Integration

In 2020 Zenith begun the “T2 Expansion” at Tanami. This expansion includes the installation of a Battery Energy Storage System (BESS) and additional gas generating units.

Once the expansion has been completed, the total Tanami project will comprise of the following:

  • 3 x Wartsila 8.7MW 20V34 Dual Fuel Generating Sets
  • 2x Wartsila 9.8MW 30V34 Gas Generating Sets
  • 4x 2.4MW Diesel Generating Sets
  • 11x 3.4MW Gas Generating Sets
  • 1 x 9.2MW / 9MWh Wartsila BESS

The BESS system will address a cyclic load demand and operate in parallel with the existing gas power station, and further reduce its carbon footprint.

Project name
Tanami
Location

Northern Territory

Client
Newmont Mining Services
Capacity
101.5 MW
Energy source
BESS, Gas, Network Infrastructure

Home

Case Studies

Daisy Milano

Daisy Milano

On 17 April 2019, Zenith Energy announced it had signed a new Power Purchase Agreement (PPA) with existing customer, Silver Lake Resources, to extend and expand its Build Own and Operate (BOO) power station at the Daisy Milano Gold Mine.

Project Background

On April 17, 2019, Zenith Energy proudly announced the signing of a new Power Purchase Agreement (PPA) with our esteemed partner, Silver Lake Resources. This agreement marks an extension and expansion of our Build Own and Operate (BOO) power station at the Daisy Milano Gold Mine.

Since 2012, Zenith has been providing Silver Lake with BOO remote power, and this new contract solidifies our partnership for an additional 4.5 years. Under the terms of the expanded PPA, Zenith will operate an 18.3MW power station, previously 12MW, comprising 13.2MW of gas-fired production and 5MW of diesel backup generation.

The PPA is scheduled to commence supply in the fourth quarter of 2019, further enhancing our total contracted BOO capacity to approximately 219MW. We consider this announcement a significant milestone for Zenith, reflecting our continued success in securing contract wins and extensions throughout the fiscal year 2019.


Project name

Daisy Milano

Location

50 km south-east of Kalgoorlie W.A.

Client

Silver Lake Resources Limited

Capacity

6.3MW, TOTAL 18.3MW

Fuel source

Gas/Diesel

CONTRACT

BOO

COMMENCEMENT

2019

Home

Case Studies

Mt Morgans

Mt Morgans

Dacian Gold’s Mt Morgans operation is located 20km west of Laverton, being approximately 750km northeast of Perth in Western Australia. The operation is amongst a very highly endowed gold field project with multi-million ounce deposits(Dacian Gold, 2022).

Project Background

Dacian Gold’s Mt Morgans operation is located 20km west of Laverton, and approximately 750km north-east of Perth in Western Australia. The operation is amongst a very highly endowed gold field project with multi-million ounce deposits (Dacian Gold, 2022).

Dacian Gold is an ASX listed company and is a mid-tier gold producer, with its main production coming from Mt Morgan, and is pursuing multiple growth options to extend the operation’s mine life along with the production of gold.

Zenith Energy is providing 19.8MW of power generation solution through the use of our gas generation sets.

The power supply commenced since 2017.

Project name
Mt Morgans
Location

Laverton, Western Australia

Client
Dacian Gold
Capacity
19.8 MW
Energy source
Gas

Home

Case Studies

Barrow Island

Barrow Island

Zenith have operated and maintained the Chevron Barrow Island Central Power Station for WA Oil since 2008.

Project Background

Zenith Energy has operated and maintained the Chevron Barrow Island Central Power Station since 2008.

The island is located approximately 60km off the north-west coast of Western Australia (WA) and approximately 88km north of Onslow in the Carnarvon Basin.

Barrow Island is home to an oil production facility as well as one of the world’s largest natural gas projects, which produces over 2.1 billion cubic feet of natural gas daily and will continue to be an important pillar of the Australian economy (Chevron, 2022).

Zenith Energy is supplying a 21MW gas power generation solution and maintains the extensive high voltage distribution system on the Island.

Project name
Barrow Island
Location

Barrow Island, Australia

Client
Chevron
Capacity
21 MW
Energy source
Gas, Network Infrastructure

Home

Case Studies

Plutonic

Plutonic

Superior Gold’s Plutonic Gold mine (the producing underground operation) is 800km north-east of Perth. It is one of the largest gold mines in Western Australia in terms of cumulative production, with both open pit and underground production.

Project Background

Superior Gold’s Plutonic gold mine (the producing underground operation) is 800km north-east of Perth. It is one of the largest gold mines in Western Australia in terms of cumulative production, with both open pit and underground production.

Superior Gold is listed under the TSX Venture exchange with 100% ownership and operation of the Plutonic Gold Operations that includes the Plutonic Gold mine.

Zenith is providing 16MW of power generation solution through the use of our gas generation sets.

The Plutonic Operation commenced production in 1990 and currently sources ore from the existing underground and open pit resources

Project name
Plutonic
Location

Western Australia

Client
Superior Gold
Capacity
43.8 MW
Energy source
Gas