Zenith Energy has successfully commissioned the gas generation plant at Mt Weld, marking a major milestone in our partnership with Lynas Rare Earths Ltd.
* Powering Ahead – Since November 2024, we have been supplying power via diesel generation, and the transition to gas-fired power is now complete.
* Early Completion – The 5 x 3.4MW gensets were commissioned and tested ahead of schedule, with full handover on 1 March 2025.
*Seamless Execution – With the LNG supply facility ready ahead of time, performance testing wrapped up smoothly in mid-February.
With the gas plant fully operational, Lynas Rare Earths Ltd has now begun its transition to gas-fired power, further enhancing reliability and efficiency at Mt Weld.
This achievement underscores Zenith Energy’s expertise in delivering high-performance, hybrid power solutions—on time and ahead of expectations.
Blogs, ESG, In the News, News
Commissioning Milestone Achieved at Mt Weld
Milestone Achieved at Mt Weld
March 28, 2025
7min
You might also like these…
Achieving a Perfect Safety Record
Blogs, ESG, In the News, News, Project Announcements & Updates
July 08, 2024
Wärtsilä – Zenith Contract Signing Ceremony: Parts Predict & Operational Support Services for Zenith Energy
Blogs, In the News, News, Project Announcements & Updates
October 25, 2024
Zenith Energy Wins Awards at Foresight Engage
ESG, In the News, News
December 20, 2024